Chemicals

Project Tripod

Client
Confidential
Project
Project Tripod
Scope
Engineering & Construction Management
Value
$72M USD
  • Capacity Increase Project for a Large Chemicals Client
  • Executed Engineering and Construction Management
  • EPC Phase Complete Based on Design Basis Documents
  • 80% of Construction Occurred During Scheduled Plant Shutdowns – From 4-18 Days
  • Jedson Team Recognized By Client for Conformity to Schedule, Cost Control and Responsiveness to Changes in Scope
  • Most Complex Shutdown Ever Undertaken at This Plant
  • 100+ Pieces of Equipment Procured / Tracked / Stored / Installed
  • Project Utilized as a Model for Future Construction Projects
  • 21 Day Shutdown Condensed to 14 Days with Pre-planning

Latest Article

How Can We Help?

Fill out the form below, and we will be in touch shortly.

How Can We Help?

Fill out the form below, and we will be in touch shortly.

How Can We Help?

Fill out the form below, and we will be in touch shortly.

How Can We Help?

Fill out the form below, and we will be in touch shortly.

How Can We Help?

Fill out the form below, and we will be in touch shortly.

How Can We Help?

Fill out the form below, and we will be in touch shortly.