PROJECT:
Kraton Chemical

Dust Hazard Mitigation Phase 2

Client:Kraton
Location:
Project:Dust Hazard Mitigation Phase 2
Scope:Engineering
Value:$13M USD

  • Conducted a multi-site capital study for combustible dust risk mitigation at Kraton’s Pensacola, Savannah, and Panama City plants.
  • Engineered safe material handling upgrades, including drag conveyors, bag fillers, and dust collection systems for terpene phenolic resins.
  • Delivered full design packages—P&IDs, 3D models, equipment specs, and electrical classification drawings.
  • Validated automation strategy and utility needs, ensuring safe, efficient process control and facility readiness.
  • Provided total installed cost estimates and execution schedules to support informed capital investment decisions.