| Client: | Confidential |
| Location: | |
| Project: | Project Tripod |
| Scope: | Engineering & Construction Management |
| Value: | $72M USD |
- Capacity Increase Project for a Large Chemicals Client
- Executed Engineering and Construction Management
- EPC Phase Complete Based on Design Basis Documents
- 80% of Construction Occurred During Scheduled Plant Shutdowns – From 4-18 Days
- Jedson Team Recognized By Client for Conformity to Schedule, Cost Control and Responsiveness to Changes in Scope
- Most Complex Shutdown Ever Undertaken at This Plant
- 100+ Pieces of Equipment Procured / Tracked / Stored / Installed
- Project Utilized as a Model for Future Construction Projects
- 21 Day Shutdown Condensed to 14 Days with Pre-planning